Pexgol: Significant Pipe Wall Scale Reduction

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Case Study Nº

137

Customer

Copper Mine
USA

|

2022

Working Conditions

Temperature: Ambient | Flow: 60 gpm — 6ft/s | Pressure: 20 psi

Pexgol Pipes

Application

Pilot Study: Scaling performance comparison between same sized Pexgol & HDPE pipes

Lenght

304 m / 1,000 ft

Categories

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Introduction

A prominent copper mine in Arizona that uses an in-situ copper ore recovery process, experienced scaling issues in the existing HDPE (PE 4710) piping deployed in the rinse cycle phase of ore extraction.
Scaling in the HDPE pipes caused clogging and despite the use of scale inhibitors and cleaning, some pipes were still being replaced too frequently.

The Problem

Increased operational maintenance and reduced efficiency of the HDPE pipes
created the need for a more efficient, long-term solution.

Pexgol Solution

Pexgol was proposed as the solution for reduced scaling.
A controlled pilot study was commissioned by the mine to compare gypsum slurry pumped through Pexgol vs HDPE (PE 4710) for a period of 4 weeks.
Various flow velocities, pressures and ambient temperatures were monitored and compared after 2 and 4 weeks.

Results

The Pexgol pipes showed almost no scaling compared with the scaled HDPE pipes after 2 and 4 weeks.
It was recommended that Pexgol replace HDPE at the rinse cycle phase of ore extraction of the mine.

Conclusion

Pexgol pipes are a viable solution for similar slurry applications.

Related Case Studies

Использование системы труб Pexgol для кормления лосося в сравнении с трубами ПЭНД

Транспортировка пищевых продуктов трубами Pexgol в сравнении с трубами ПЭНД

Компания Marine Farms
Чили

 | 

2017
Addressing Scaling and Line Plugging with Advanced PE-X Piping.

Slurry: Pexgol’s Superior Alternative to Traditional Piping

Chip Manufacturer
USA

 | 

2022
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023