The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Case Study Nº

137

Customer

Copper Mine
USA

|

2022

Working Conditions

Temperature: Ambient | Flow: 60 gpm — 6ft/s | Pressure: 20 psi

Pexgol Pipes

Application

Pilot Study: Scaling performance comparison between same sized Pexgol & HDPE pipes

Lenght

304 m / 1,000 ft

Categories

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Introduction

A prominent copper mine in Arizona that uses an in-situ copper ore recovery process, experienced scaling issues in the existing HDPE (PE 4710) piping deployed in the rinse cycle phase of ore extraction.
Scaling in the HDPE pipes caused clogging and despite the use of scale inhibitors and cleaning, some pipes were still being replaced too frequently.

The Problem

Increased operational maintenance and reduced efficiency of the HDPE pipes
created the need for a more efficient, long-term solution.

Pexgol Solution

Pexgol was proposed as the solution for reduced scaling.
A controlled pilot study was commissioned by the mine to compare gypsum slurry pumped through Pexgol vs HDPE (PE 4710) for a period of 4 weeks.
Various flow velocities, pressures and ambient temperatures were monitored and compared after 2 and 4 weeks.

Results

The Pexgol pipes showed almost no scaling compared with the scaled HDPE pipes after 2 and 4 weeks.
It was recommended that Pexgol replace HDPE at the rinse cycle phase of ore extraction of the mine.

Conclusion

Pexgol pipes are a viable solution for similar slurry applications.

Related Case Studies

Sewage Water Transportation With 300 Ppm Hydrogen Peroxide

Sewage Water Transportation

BorsodChem
Hungary

 | 

2011
Potable Water Supply on Harsh Terrain

Снабжение питьевой водой в труднопроходимой местности

Компания водоснабжения Mekorot / Beit Shemesh Water Company
Израиль

 | 

2017
Transport of acid slurry at high temperatures

Транспортировка суспензии

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2012
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018
В аэропорту Гайаны был установлен наружный гидрант и спринклеры внутри помещений

Линия водоснабжения и пожарной воды

Международный аэропорт Cheddi Jagan
Гайана

 | 

2018
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023