Skip to content

Navigating extreme conditions with Pexgol’s PE-X pipes

The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Case Study Nº

151

Customer

Anglo American Perú
Peru

|

2023

Working Conditions

Temperature: 15°-20°C (59° — 68°F) | Flow: 450 m^3/h | Pressure: 22 bar | Fluid components: Tailings with high percentage of solids 70%CW

Pexgol Pipes

Pexgol 14″, SDR 11

Application

Tailings transportation in copper mining

Lenght

180 m / 590 ft

Categories

Navigating extreme conditions with Pexgol’s PE-X pipes

The Challenge

In 2023, Anglo American Peru, a global mining leader, faced a significant challenge at its Quellaveco mine. The existing HDPE pipeline, designed for transporting copper tailings with high solids (70%CW) at a temperature of 15-20°C (59-68°F), a flow rate of 450 m³/hr, and a pressure of 22 bar, required an urgent upgrade. The pipeline needed to be rapidly installed on a steep slope with a 60-meter (197-foot) drop, to enhance the capacity of the concentrator plant and integrate cyclones into the system.

Pexgol Solution

The 14-inch PE-X pipes from Pexgol, with a total length of 180 meters in two segments of 90 meters each, were the chosen solution. Using Pexgol fittings like Electrofusion Couplers, Stub Ends, and Support Bridges, the installation was completed in approximately 7 days by a specialized team. The process involved a Pexgol vertical uncoiler and two cranes, ensuring a quick and efficient setup. The critical benefits of the Pexgol piping system, such as quick installation, high chemical and corrosion resistance, lightweight handling, and long lengths, were key to making it ideal for the project.

Related Case Studies

Сокращение накопления отложений - высококонцентрированный известковый раствор

Технологическая вода — транспортировка рассола

SQM Nueva Victoria Iquique
Чили

 | 

2010
Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Уменьшение нарастания материала в линиях рассола и раствора кислоты

Переработка полезных ископаемых. Транспортировка рассола

Компания SQM, шахта Pedro Valvidia
Чили

 | 

2010
Транспортировка воды под высоким давлением для золотого рудника.

Транспортировка воды под высоким давлением

Рудник Mansfield
Аргентина

 | 

2019
Фитинги Pexgol для транспортировки рассола в бразильской химической компании.

Высокая коррозионная стойкость к рассолу

Unipar Carbocloro
Бразилия

 | 

2019
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022