Improvement in Brine Management through Pexgol Piping

The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Case Study Nº

128

Customer

Sales de Jujuy
Argentina

|

2023

Working Conditions

Temperature: Variable

Pexgol Pipes

Pexgol 160 mm (6″), Class 15

Application

Brine Transport

Lenght

2650 m / 8692 ft

Categories

Improvement in Brine Management through Pexgol Piping

The Challenge

Sales de Jujuy S.A. is the operating company of the main Olaroz Lithium Project by Orocobre in Argentina. This facility is located in the province of Jujuy, at an altitude of 3,900 meters above sea level, and produces lithium carbonate from the brine of the Olaroz Salt Flat, which contains high concentrations of lithium and potash. The transportation of brine from the lithium well posed a significant challenge for the company.

The problem lay in the existing HDPE pipeline, which experienced a pump performance drop three times a month when pumping brine. This situation was caused by pipe clogging due to scale buildup, requiring cleaning that consumed six working days per month. This not only disrupted regular operations but also incurred significant costs for the company.

Pexgol Solution

To address this challenge, Sales de Jujuy decided to switch to 160 mm Pexgol piping. They installed 2650 meters of this piping, using double mechanical connectors.

The choice of Pexgol was due to several advantages that this product offered. Firstly, its quick installation significantly reduced the time required for project implementation. Additionally, Pexgol piping is known for its low roughness, which considerably reduces scale buildup.

This change to Pexgol brought immediate and significant results. Line cleaning times and the number of interventions were drastically reduced. In fact, the cleaning time was reduced to only two hours per month, and only at the connections.

Related Case Studies

Монтаж сети пожаротушения на нефтеперерабатывающем заводе.

Водоснабжение для пожарных сетей

КНМ
Аргентина

 | 

2021
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Транспортировка высококоррозийных материалов от сгустителей на установку нейтрализации

Транспортировка коррозионных материалов

Компания Moa Nickel S.A, Sherritt
Куба

 | 

2015
Откачка воды без опор

Откачка воды из карьера

Компания Arcelor Mittal, шахта El Volcan
Мексика

 | 

2017
Монтаж труб Pexgol для транспортировки рыбы.

Линии разгрузки рыбы

TASA
Перу

 | 

2018
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022