Skip to content

Efficient Choice: PE-X Pipe for the Palm Industry

Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Case Study Nº

120

Customer

Extractora Monterrey
Colombia

|

2023

Working Conditions

Flow: 50 m3/h | Temperature: 80°C / 176°F

Pexgol Pipes

Pexgol 110 mm (4″), class 15

Application

Muddy water transport

Lenght

200 m / 656 ft

Categories

The Challenge

The agroindustrial Colombian company Extractora Monterrey S A S is dedicated to the cultivation and processing of palm fruit, for the extraction of crude oil, palm kernel oil and palm kernel cake. It required the installation of a new line to transport muddy water to the oxidation ponds. From the Florentine passing the main road and the plantation, the excavation and installation of the pipe would be carried out in the crop, between palm trees without causing damage to the plants and the irrigation pipe.

Pexgol Solution

In this case, PE-X pipes were chosen because they are cheaper compared to the installation of stainless steel pipes.

Another factor that influenced the decision to use PE-X pipes was its ease of installation. The installation process was quick and easy, allowing the 200 meters of pipe to be laid in just 4 hours, using only two 15/16 wrenches, a level and a GP mechanical union.

In addition, PE-X pipes have fewer joints, which reduces the risk of leaks and therefore increases efficiency in transporting palm oil.

Finally, the recommendation of another client who had used PE-X pipes in other projects with good results also influenced the decision to use this type of pipe in the installation.

In summary, the choice of PE-X pipes in the transport of slurry water is due to its lower cost compared to stainless steel pipes, its ease of installation, fewer joints, recommendation from other clients and the speed of delivery. placement, which reduced the time and number of personnel required for installation.

Related Case Studies

Монтаж труб Pexgol для вертикального дренажа

Вертикальный отвод вод

Полтавский ГОК, Ferrexpo
Украина

 | 

2019
Монтаж труб Pexgol на установке подготовки пластовой воды.

Установка водоподготовки для вторичной закачки

YPF
Аргентина

 | 

2020
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018
Транспортировка спирта концентрацией до 86% для производства рома и бренди

Транспортировка спирта для производства рома и бренди

Cuba Ron
Куба

 | 

2016
Откачка воды без опор

Откачка воды из карьера

Компания Arcelor Mittal, шахта El Volcan
Мексика

 | 

2017
Replacement of a Drainage Line in an Underground Mine.

Дренаж в подземном руднике

Atacama Kozan
Чили

 | 

2019