Well Drainage at Mining Dam

Installation of a Drainage System between a Well and a Mining Dam.

Estudo de Caso Nº

78

Cliente

CODELCO – El Teniente Mine
Chile

|

2019

Condições de Trabalho

Extreme temperatures -5° to 35°C / 25° to 95°F

Solução Pexgol

Pexgol 250 mm (10”), class 15

Aplicação

Dewatering

Comprimento

1620 m / 5314 ft

Categorias

Installation of a Drainage System between a Well and a Mining Dam.

The Challenge

The administration of the Carén reservoir, in the commune of Alhué (Chile), receives tailings from the El Teniente mine.

The western retaining wall of the reservoir needed to be widened by at least 30 meters. In order to do that a well had to be drained that was formed by leaks from the wall at its base. The extracted water had to be returned to the dam.
Also, the drainage work had to be done in just 20 days.

Pexgol Solution

The customer finally opted for Pexgol, despite the higher cost per meter, because the final cost of the installation, that only took one week, was widely offset against the installation of HDPE pipe that would have taken about a month and a half.

The advantage of Pexgol, in this solution, lies in the supply format in coils of long lengths, which made it possible to streamline its layout in the field, with no more than a dozen couplings, thus reducing assembly time.

In addition to the quick installation, technical assistance from the local team (Crosspipe Systems) was carried out with great agility and efficiency.
A total of 11 electrofusion fittings were installed.

Estudos de Caso Relacionados

Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Navigating extreme conditions with Pexgol’s PE-X pipes

Anglo American Perú
Peru

 | 

2023