Water Transport Between Dams
Installation of a Drainage System between Dams in a Copper Mine.
Estudo de Caso Nº
77
Cliente
|
Condições de Trabalho
Solução Pexgol
Aplicação
Comprimento
Categorias
The Challenge
Cooperación del Cobre de Chile (CODELCO) required transporting water from the Barahona dam to a specific sector of the Caletones smelter, located south of the dam. The line was due to be installed in less than 10 weeks.
The distance of the route, in addition to other works being carried out on site and the vehicular flow, made it critical that the pipeline needed to be installed in the shortest time possible.
Pexgol Solution
The client made an economic evaluation, considering the installation time of the HDPE versus PE-X pipes from Pexgol. Pexgol was finally chosen.
The delivery format in coil of long lengths, allowed the totality of meters to be delivered in only 10 coils.
Installation was exceptionally fast. The uncoiling allowed up to 6 drums per day to be released, the sections to be located in their final location and subsequently joined with the relevant couplings, within 6 days.
As for the accessories, 9 electrofusion couplings were used.
The final experience was very satisfying.
Estudos de Caso Relacionados
Fiber Optic Cables Through a Vertical Shaft
|
Recovered Water Transportation
|
Water Transport Between Dams
|
Efficient Open Pit Mine Drainage
|