Transportation of sodium sulfide

Pvc Pipe Replacement by Pexgol

Estudo de Caso Nº

44

Cliente

Magnelec S.A. de C.V.
Mexico

|

2018

Condições de Trabalho

Pressure 60 psi; Temperature 60° to 80°C; Highly Corrosive Liquid

Solução Pexgol

Pexgol 225×20.4 SDR 15

Aplicação

Sodium Sulfide Transportation

Comprimento

600 meters

Categorias

Pvc Pipe Replacement by Pexgol

The Challenge

Magnelec had installed a Yellomine pipe (PVC pressure pipe) where it was transporting sodium sulfide.
Due to changes in temperature in the fluid, dilatation and contraction of the pipe was frequent issue. The pipe was installed in sections of 6 metersc each, generating leaks in the joints, which caused a lot of losses in the line of conduction. Also, there were problems in the stainless steel pipes with leaks in the joints of the welds.

Pexgol Solution

Due to this frequent problems, Magnelec decided to replace its pipes with Pexgol. Once the Yellomine pipes were replaced by Pexgol pipes, the problem of leakage was solved, thanks to the fact that Pexgol pipes were supplied in rolls of great lengths, which decreased the number of joints. The material of Pexgol pipes is flexible and absorbs the movements that can be generated by changes in temperature.
They are also highly resistant to corrosion and to high and low temperatures, so it was the ideal solution.
The installation was quick and easy in sections of 200 meters in length with mechanical GP connections. The installation took around 7 days. The tools used were tightening wrenches, slings, crane, etc.

Estudos de Caso Relacionados

Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Process Plant: Transport of Leached Slurry

Barrick Gold – Pueblo Viejo
Dominican Republic

 | 

2018