Transport of Muddy Water for Palm Oil Extractor

Pexgol pipe was selected for the assembly of a muddy water transport line for a palm oil processing company.

Estudo de Caso Nº

121

Cliente

Extractora Poligrow
Colombia

|

2022

Condições de Trabalho

Flow rate: 176 PSI | Temperature: 80°C / 176°F

Solução Pexgol

Pexgol 110 mm (4″), Class 15

Aplicação

Transport of Muddy Water

Comprimento

550 m / 1084 ft

Categorias

Transport of Muddy Water for Palm Oil Extractor

The Challenge

Poligrow Colombia is a company dedicated to the development of agro-industrial projects, focused on palm oil extraction.

Poligrow needed a new transport line for muddy water to the oxidation lagoons. For this purpose, excavation and installation of the piping was carried out in the palm crop, without causing damage to the plants or irrigation piping. The route of the piping extended from Florentino, passing through the main road and the plantation

Pexgol Solution

Poligrow opted to use Pexgol’s PE-X piping for the transport of muddy water. The choice of Pexgol was crucial to finish the project quickly and efficiently.

Pexgol was chosen for several reasons: firstly, the installation was quick and simple, which saved time and costs. Additionally, the use of PE-X piping reduced the number of necessary joints, further simplifying the installation.

Another advantage was the supply in a 550-meter roll, which minimized the need for additional cuts and joints. The installation of the 550 meters of piping was carried out in a record time of 7 hours, thanks to the efficiency and simplicity of the process.

To carry out the installation, two GP mechanical joints were used, and support was provided by a CAT 312 backhoe, a Benitin vibrocompactor, and a ratchet. In addition, the technical team responsible for the installation consisted of one officer and one assistant.

In summary, the choice of Pexgol and its PE-X piping for the transport of muddy water in the palm oil processing plant was a wise decision, as it allowed the project to be completed quickly, efficiently, and with minimal interruptions.

Estudos de Caso Relacionados

The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Innovation and improvement in fluid transportation in the oil and gas industry.

Streamlining Effluent Treatment with Pexgol

Pan American Energy
Argentina

 | 

2023
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019