Safety and durability: The heart of our solutions

Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Estudo de Caso Nº

153

Cliente

Minera Fresnillo
Mexico

|

2021

Condições de Trabalho

Pressure: 130 psi (pump pressure) | Temperature: Ambient 35°C / 95°F | Fluid: Slurry (tailings), concentration 55%

Solução Pexgol

Pexgol 280 mm (12″), SDR 11

Aplicação

Tailings transportation

Comprimento

4800 m / 15748 ft

Categorias

Safety and durability: The heart of our solutions

The Challenge

Fresnillo, a leader in silver and gold production in Mexico, faced significant issues with its existing HDPE pipeline in its mining unit. Frequent failures in mechanical joints, including detachments of stub ends, failures in thermal fusions and flanges, created a potential risk of tailings spills, raising concerns for safety and environmental impact.

Pexgol Solution

Pexgol addressed this challenge with its scientifically proven and abrasion-resistant PE-X pipes, being up to four times more resistant than HDPE.

The electrofusion joints in Pexgol pipes ensured double safety, significantly reducing the risk of leaks. The installation was remarkably efficient, with each 120-meter roll laid out in just 20 minutes, allowing for rapid progress without compromising safety or quality.

A crucial aspect of Pexgol’s service was the comprehensive training provided to Fresnillo mine staff. This training ensured that the personnel were skilled in handling and installing Pexgol pipes, particularly mastering the electrofusion process. This skill development initiative not only facilitated smoother installations but also empowered the mine team with the knowledge and confidence to maintain pipeline integrity, reflecting Pexgol’s commitment to excellence and collaboration in every project.

Estudos de Caso Relacionados

The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022