Recovered Water Transportation
Grey Water Transportation
Estudo de Caso Nº
38
Cliente
Coeur Mexicana S.A. de C.V. Palmarejo
Mexico
|
2017
Condições de Trabalho
74 psi, altitude dierence= 34 m, Au= 0.12 ppm, Ag= 0.18 ppm, Cu= 1.13 ppm, Fe= 0.73 ppm, Cn total= 1.5 ppm, Ca= 458 mg/dL, Ph= 8
Solução Pexgol
Pexgol SDR 15 225 x 20.4.
Aplicação
Water transportation.
Comprimento
1200 meters.
Categorias
The Challenge
Coeur Mexicana required to transport recovered water, but they wanted to conduct an installation in the minimum time possible that won’t require contractors, specialized personnel neither expensive equipment.
Pexgol Solution
The client decided to install Pexgol, due to it quick and easy installation, that if was carried out with steel or HDPE pipes, it would require 100 joints. But, since it was done with Pexgol pipes it only took 4 joints.
Furthermore, it was considered the security that Pexgol pipes offer, since it’s supplied in long length coils, which reduces leakages.
Pexgol’s team advised the client during the whole process from the design to the installation.
Estudos de Caso Relacionados
Transport of Silica Arena: HDPE vs Pexgol
Covia Corp
Mexico
|
2019
Underground Mine Dewatering
Codelco Chuquicamata
Chile
|
2017
High Corrosion Resistance Against Brine
Unipar Carbocloro
Brazil
|
2019
Installation of Water Well in Reduced Space
Mekorot
Israel
|
2020