Overcoming Geotechnical Challenges with Pexgol at Media Luna

Improving drainage in the Media Luna mine with Pexgol.

Estudo de Caso Nº

159

Cliente

Minera Media Luna
Mexico

|

2023

Condições de Trabalho

Temperature: 25°C / 77°F | Flow: 80 l/sec | Pressure: 28.5 bar

Solução Pexgol

Pexgol 8″ SDR 6

Aplicação

Mine Dewatering

Comprimento

540 m / 1640.42 ft

Categorias

Overcoming Geotechnical Challenges with Pexgol at Media Luna

The Challenge

Torex Gold, an intermediate gold producer with operations in the Guerrero gold belt in Mexico, faced a significant challenge at its Media Luna mine. The need for an effective underground water pumping system was critical to continuing mining operations. The conventional alternative of using steel pipes presented multiple disadvantages, including the high cost of installation and materials, the need for frequent welding every 12 meters, and the requirement for specialized machinery for installation inside the mine, in addition to susceptibility to corrosion due to high humidity in the underground environment.

The Solution

After a thorough analysis, Torex Gold selected 8” SDR 6 Pexgol pipes for a total of 540 metres distributed in two coils of 270 metres each. Pexgol pipes were chosen for their corrosion resistance, the possibility of supplying them in long sections that significantly reduce joints, and their fast and efficient installation. In addition, the lightness and flexibility of the material facilitated its handling and installation in the complex mine environment.
The implementation of the Pexgol solution at Minera Media Luna not only met the operational and technical requirements of the project, but also exceeded expectations in terms of installation efficiency and costs. The ability to supply pipes in long coils allowed for continuous installation without the interruptions and costs associated with welding required by steel pipes. In addition, the mine’s in-house engineering successfully designed the surface base and the clamping platform at the end of the countershaft, ensuring seamless integration of the Pexgol system into the existing infrastructure. This project not only demonstrated the technical and economic viability of Pexgol pipes in challenging mining applications, but also set a precedent for future implementations, highlighting the importance of selecting innovative materials that offer durable and cost-effective solutions in the mining industry.

Estudos de Caso Relacionados

Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Carriage of Chemicals at Sea Port

Ashdod Sea Port
Israel

 | 

2016
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Química del Rey replaced a corroded steel column with a Pexgol line, achieving a faster, safer, and more durable installation.

Reliable Solution for Deep Wells in Corrosive Environments

Química del Rey
Mexico

 | 

2022
Water Drainage in Harsh Ground

Water Drainage at an Open-Cast Mine

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

 | 

2016