Skip to content

Open Cast Mine Dewatering

Water Transportation through Shafts

Estudo de Caso Nº

39

Cliente

Agnico Eagle Pinos Altos Mine
Mexico

|

2017

Condições de Trabalho

300 psi, altitude dierence= 174 m, mine water with 15-20% solids.

Solução Pexgol

Pexgol SDR 7.4 225×30.8.

Aplicação

Dewatering.

Comprimento

225 meters.

Categorias

Water Transportation through Shafts

The Challenge

The ground water control system used at Pinos Altos Mine is trough dewatering, which is the method that better adjust to the characteristics of the mine work, furthermore it’s the more efficient and cost-effective if it’s handled the right way.

The fluid transportation associated costs in the mining industry represents an important percentage of the total cost of the operation, consequently the development of work schemes and a hydraulic system optimization, generates important savings on operational costs.

For the pumping system optimization the client designed a pool on level 28, that will gather the runoff water from the superior levels after pumping up to level 22.

Pexgol Solution

For this conduction line a Pexgol pipe was chosen, since it fulfilled the technical features that the job required. Due its ability to be supplied in long length coils, and its capacity to hold 175 meters of water column (249 psi), plus its easy-to-maneuver and installation capabilities (since the pipe was installed through the shafts) and its supplied long sections (which prevents head losses through the joints), the Pexgol pipe was the perfect solution. In addition, the Pexgol pipe roughness coefficient is lower than other pipes, therefore less friction losses and energy savings were encountered.

Estudos de Caso Relacionados

Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023