Skip to content

Natural Gas Transportation with Pexgol

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Estudo de Caso Nº

110

Cliente

YPF
Argentina

|

2022

Condições de Trabalho

Fluid: Condensate natural gas | Temperature: 35°C / 95°F | Minimum Pressure: negative (vacuum) | Maximum Pressure: 2 kg/cm2 | Flow: 40.000 standard m3/d

Solução Pexgol

Pexgol 160 mm (6”) , class 10

Aplicação

Natural gas transportation

Comprimento

600 m / 1968 ft

Categorias

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

The Challenge

YPF is an Argentine energy company dedicated to the exploration, exploitation, distillation, distribution and production of electricity, gas, oil and other products related to the industry.

In its Vacas Muertas oil field, province of Mendoza (Argentina), the company had to replace 600 meters of carbon steel pipe, located between the crude oil treatment plant (PTC) and the gas compression plant. Over time, the section had reduced its internal diameter at different points of the trace, due to encrustations caused by corrosion and deposits resulting from humid gas condensation. This reduced the gas flow, and there was a risk of reaching a total obstruction of the flow.

As it is a continuous process, which does not allow accumulation of gas, it was necessary to carry out the work as quickly as possible with the shortest time of interruption of the flow to the gas plant.

Pexgol Solution

It was decided to install Pexgol pipes, which allow a quick installation and with the minimum amount of resources. This way, the corrosion process will be avoided, as well as the accumulation of scale due to the low absolute roughness of the internal walls of Pexgol pipes, allowing a continuous flow without obstructions over time.

The installation was completed with 3 coil of Pexgol 160 mm Class 10 pipe, the joints were made with electrofusion couplings, and the steel transitions with Pexgol flaring (stub-ends).

The installation was carried out in two working days, aerially on existing trestles, and with a minimum interruption of the process. The resources used were minimal: 3 operators with an uncoiler, a hydrocrane and a backhoe. The replacement with carbon steel would have taken a month with the company’s operational resources, and with a total cost 6 times higher than that required for the materials and installation with Pexgol pipes.

Estudos de Caso Relacionados

Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019
O sistema de tubulação da Pexgol permitiu que a Nexa Resources renovasse seu processo de gerenciamento de resíduos, reduzindo significativamente o impacto ambiental.

Aprimorando a Gestão de Resíduos da Nexa Resources Usando Pexgol

Nexa Resources
Brasil

 | 

2023
Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Mine Dewatering at Low Temperature

Ferrexpo Yeristovo Mining
Ukraine

 | 

2019
Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022