Skip to content

Mine Dewatering at Low Temperature

Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Estudo de Caso Nº

61

Cliente

Ferrexpo Yeristovo Mining
Ukraine

|

2019

Condições de Trabalho

Vertical installation, ground laying on hills. Ambient temperature: -15°C to 4°C

Solução Pexgol

Pexgol 280 mm (10”), Class 15

Aplicação

Mine Dewatering

Comprimento

360 m

Categorias

Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

The Challenge

Ferrexpo Yeristovo Mining needed to install mobile long sections of pipeline for mine dewatering. They requested that the pipe should have scratch resistance and can be installed on the rocks without any complicate preparations.
They used to work with steel pipes but they presented serious problems such as:

  1. Corrosion
  2. Difficult and expensive installation
  3. Long disassembly and replacement time

Pexgol Solution

The client chose Pexgol pipes with 280 outside diameter, class 15 in coils of 120 meters each with mechanical couplers for a fast and efficient installation. During the installation a 60 ton Hitachi bulldozer and a Manitou telehandler were used for decoiling.

There were 3 separated lines of one piece of 120 meters each without any additional connectors. The only connection was a flange coupler with a pump outlet. Pipes were fixed on top and in the middle by fixpoint clamps as well.

The use of Pexgol pipe solutions allow the client to save costs (manpower and installation time).

Estudos de Caso Relacionados

Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019
Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020