Skip to content

Meltdown Water Transport

Pipe installation on a mountain

Estudo de Caso Nº

16

Cliente

Codelco Andina, TADA 1-2 Project
Chile

|

2013

Condições de Trabalho

Complex & harsh ground, 300 m altitude.

Solução Pexgol

Pexgol 315 mm, Class 15 (SDR 11).

Aplicação

Water transportation.

Comprimento

3,300 m.

Categorias

Pipe installation on a mountain

The Challenge

Codelco needed to transport meltdown water downhill at Andes Mountain range.

The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.

Pexgol Solution

Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.

The installation was simplified by the use of Pexgol long sections.

The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.

The installation was done in perfect timing with an optimal performance.

Estudos de Caso Relacionados

Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
  • 2
  • 3
  • 4
  • 5
  • 6