Codelco Andina, TADA 1-2 Project
Chile

|

2013

Condições de Trabalho

Complex & harsh ground, 300 m altitude.

Solução Pexgol

Pexgol 315 mm, Class 15 (SDR 11).

Aplicação

Water transportation.

Comprimento

3,300 m.

Categorias

Pipe installation on a mountain

The Challenge

Codelco needed to transport meltdown water downhill at Andes Mountain range.

The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.

Pexgol Solution

Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.

The installation was simplified by the use of Pexgol long sections.

The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.

The installation was done in perfect timing with an optimal performance.

Estudos de Caso Relacionados

Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015