Installation of Water Well in Reduced Space

Installation of a Borehole with Pipe in Sections for Reduced Space.

Estudo de Caso Nº

95

Cliente

Mekorot
Israel

|

2020

Condições de Trabalho

Pressure: 10 bar

Solução Pexgol

Pexgol 200 mm (6”), class 24

Aplicação

Borehole for treated effluent water

Comprimento

70 m

Categorias

Installation of a Borehole with Pipe in Sections for Reduced Space.

The Challenge

Mekorot, the national company in charge of water supply in Israel, among other activities, has installed and used Pexgol pipes for water wells for more than 30 years.

The wells were always installed using one of Pexgol’s great advantages, which is the possibility of supplying the pipes in coils of long lengths.

For this project in particular, the well had to be installed in a central area of the city and therefore there was not enough space to carry out the coil deployment. The pipe needed to transport treated effluent water.

Pexgol Solution

Together with the Engineering Department of Golan Plastic Products, low cost accessories were developed in order to be able to install the pipes in 12 meter lengths and thus occupy as little space as possible on public roads for installation.

The accessories consisted of a stainless steel “insert” and our Double Connector made of galvanized iron coated on the outside with anti-corrosive paint. Although long sections were not supplied, the fact of installing Pexgol pipe guarantees a long lifespan, which could not be achieved if it was done with conventional steel pipes.

The installation was a success and only took one working day, to make the connections the team did not require special tools or previous training.

Estudos de Caso Relacionados

Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Replacement of Carbon Steel Pipe for a Pexgol Pipe

Water Transportation

Cargill
Mexico

 | 

2017
Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017