Gas Wells: Formation Water Treatment

Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Estudo de Caso Nº

64

Cliente

Canacol
Colombia

|

2018

Condições de Trabalho

Water with gas and minerals | Pressure: 15 bar | Temperature: 20°C

Solução Pexgol

Pexgol 160 mm (6”), Class 15

Aplicação

Formation water transportation

Comprimento

11 Km

Categorias

Installation of Pexgol pipes for the transport of formation water (gas and minerals)

The Challenge

Canacol together with the engineering company A.B. Projects had the mission of creating new wells for gas extraction and transporting it for distribution in Cordoba, Colombia.
Due to the high pressure for the gas transportation (above 100 bar) the client used Flexsteel (flexible pipes made of layers of polyethylene and steel). Additionally, at the exit of the wells, the gas had to be separated from the water that was underground through a turbine. But the separated water still contained traces of gas and minerals that needed to be treated once again.

Pexgol Solution

Canacol and A.B. wanted to use a reliable pipe to carry out the separation of water from surplus gases and minerals, but having used the Flexsteel pipe would have incurred on excessive expenses. Therefore they selected Pexgol thanks to its possibility of supply in long lengths, its high levels of safety and its low installation cost (versus other materials for high and low pressures).

The 11 km of pipe were installed in just one week: the uncoiling and laying of the pipes took 3 days and then the joints were connected by electrofusion and the pipes buried.

Pexgol proved once again to be an excellent solution for oil or gas wells where it is required to transport water for treatment with pressures that are below 30 bar.

Estudos de Caso Relacionados

Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021