Facing the Challenges of the Neuquén Terrain in Argentina

Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Estudo de Caso Nº

145

Cliente

Pluspetrol
Argentina

|

2023

Condições de Trabalho

Temperature: 20°C / 68°F | Pressure: 10 bars | Flow: 30m3/h | Components: River water

Solução Pexgol

Pexgol 110 & 160 mm, class 15

Aplicação

Water transport

Comprimento

13300 m / 43773 ft

Categorias

Facing the Challenges of the Neuquén Terrain in Argentina

The Challenge

Pluspetrol and JMAC Resources, both giants in their respective domains, embarked on Yacimiento La Caleta in Neuquén, Argentina, with a mission. The objective was clear: to install an aerial pipeline that would last for a year and withstand both pressure and weather conditions. Without an existing line for this project, they faced the challenge of erecting a robust but temporary water transport system, ensuring it could handle the demands of transporting river water at 20°C (68°F) and a pressure of 10 bars.

Pexgol Solution

To address this formidable challenge, the Pexgol 110-160 mm, class 15 pipeline emerged as the ideal solution. Spanning a vast length of 13,330 meters (43,773 feet), this pipeline offered the benefits of quick installation, lightweight handling, and extended sections.

Not only was the installation process streamlined to just one week using the unroller provided by Argpex, but on-site training was also given to JMAC for Pluspetrol. This ensured expert handling of Pexgol’s mechanical joints and a seamless integration process. The testament to its success was not only the efficient water transport but also the excellent after-sales service, reinforcing the brand’s commitment to quality and customer satisfaction.

Estudos de Caso Relacionados

Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Improving drainage in the Media Luna mine with Pexgol.

Overcoming Geotechnical Challenges with Pexgol at Media Luna

Minera Media Luna
Mexico

 | 

2023
Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023