Efficient Open Pit Mine Drainage
Pexgol Pipe Installation for Open Pit Mine Drainage.
Estudo de Caso Nº
108
Cliente
|
Condições de Trabalho
Solução Pexgol
Aplicação
Comprimento
Categorias
The Challenge
BHP at its Escondida mining unit needed to drain water from inside its open pit mine to the outside. The client used to use conventional HDPE pipes in 12-meter strips in its operations, which requires long installation times, joints and associated resources.
Pexgol Solution
The client decided to replace its conventional HDPE pipes with Pexgol, which could be supplied in long sections (200 m), which allowed and facilitated installation. Likewise, Pexgol allowed the use of fewer joints for the total section.
An unwinding time of 200 meters was calculated, in 40 minutes set at the end point. The same amount of meters in pipes with strips of 12 meters, they achieved it in 14 days, that is, 20,160 minutes.
Performance
Tubería HDPE= 200 m / 20160 min = 0,6 m/hr
Tubería Pexgol= 200 m / 40 min = 300 m/hr
Pexgol performance 504 times more efficient.
Estudos de Caso Relacionados
Vertical Drain in Underground Mine
|
Transport of Compressed Air for Underground Mine
|
Potable Water Aqueduct
|
Industrial Waste Water to MBR Treatment Facility
|