Skip to content

Corrosive Material Transportation

Transport of high corrosive material from the thickeners to the neutralization plant

Estudo de Caso Nº

23

Cliente

Moa Nickel S.A. Sherritt
Cuba

|

2015

Condições de Trabalho

70° C, 11 bars.

Solução Pexgol

Pexgol 500 mm, Class 15 and Pexgol 450 mm, Class 15.

Aplicação

Transportation of corrosive material.

Comprimento

150 m.

Categorias

Transport of high corrosive material from the thickeners to the neutralization plant

The Challenge

Moa Nickel required to transport high corrosive material from the thickeners to the neutralization plant tanks. Originally, they used to do it through a 18 and 16 inches carbon steel line (A53, Gr.B, Sch10), with welded joints and 1/4” rubber lined. The pipe consisted in short pipe sections, 6 meters long each one, approximately 150 meters total length. It was used until it was practically destroyed as a consequence of the corrosion and wear. The engineering team decided that it needed to be replaced before it could affect the production.

Pexgol Solution

Golan presented a quick-to-install solution for the complete substitution of the line. The design included standard and special Pexgol fittings, elbows, Tee instruments and more than 150 meters of pipe. The Pexgol pipe was installed in the same spot as the former carbon steel pipe, improving the supports.

The former carbon steel pipe was 50% more expensive than Pexgol, which also was more convenient and easy to install, saving time and money for its installation.

 

Pipe TypePexgol Cost vs OthersPexgol Total Investment Costs vs Others
Rubbed steel A53 Gr, B Sch. 201:1.41:2
Stainless steel 316L, Sch. 201:21:3
Titanium B862, Gr.2, 3 mm thk1:2.31:3.2
Polypropylene PP-H, SDR 171:3.81:4.2

Estudos de Caso Relacionados

An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Water Supply & Fire Extinguisher Line

Cheddi Jagan International Airport
Guyana

 | 

2018
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018