Backfill

Cement Slurry Injection to an Underground Mine

Estudo de Caso Nº

35

Cliente

Aguilar Mine
Argentina

|

2015

Condições de Trabalho

Fluids: Cement 450.2 g; Water 500 ml; Volume 670 cm.; Density 1.4 t/m. Pressure: Temporary pressures up to 33 k/cm2. Height difference: 300 meters.

Solução Pexgol

Pexgol 110 mm (4”) Class 24 (SDR 7.4).

Aplicação

Backfill

Comprimento

1,400 meters.

Categorias

Cement Slurry Injection To An Underground Mine

The Challenge

Due to this special circumstances, the client requested Pexgol pipes since they can be provided in 600 meters sections, they are flexible and highly resistant to abrasion and impacts.

The pipe sections were uncoiled hundreds of meters from the installation place, later they were descended with a hydraulic crane.

The end of the pipe was connected with a conical weight used as a guide to help it descend trough the robbins.

The ground was very harsh with sharp rocks, however the pipes were dragged, pulled and descended without problems.

The pipes were practically hanging from the surface of each level on the mine, supported by electro-fusion couplers. Despite the complicated conditions, the installation took only 60 net hours of work.

Pexgol Solution

Pexgol pipes were the optimal solution for this project, because it can be supplied in long lengths coils that makes the whole installation easier.

Pexgol is also known for its stress resistance, Pexgol’s crosslinking piping solution can withstand high amounts of axial and radial stresses, it only stretches up to 2% of its own length and it is capable to hold its own weight plus the water column.

Due to it great flexibility, the coil was uncoiled hundreds of meters away from the installation place, and it was dragged after to the right spot.

In order to descend the pipe through the open cast, it required only chains and a backhoe to hold it. Arcelor Mittal was very satisfied with the installation process, which was simple, and from their point of view, impossible to do it with other type of pipe.

Estudos de Caso Relacionados

Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015
Water transportation with sulfide and cobalt particles

Water and Sulfide Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Installation of Pexgol Pipes in a Fish Processing Plant.

Fish Oil Transport at 36°C / 96.8°F

Guaymas Protein Company
Mexico

 | 

2018
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018