Skip to content

Water Supply & Fire Extinguisher Line

An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Estudo de Caso Nº

49

Cliente

Cheddi Jagan International Airport
Guyana

|

2018

Condições de Trabalho

Water: 6 bar | Hydrants: 12 bar Indoor | Sprinklers: 18 bar

Solução Pexgol

Pexgol 110, 125, 160 & 225 mm 32 Class 19

Aplicação

Water Supply & Fire Extinguisher Line

Comprimento

Categorias

The Challenge

Cheddi Jagan International Airport were going under renovations in order to expand their operations.
One of the main challenges for them was installing a fire extinguishing line all over the airport. The main concern for the engineering company (China Harbour) that was caring out the project was to find a suitable pipe line that required minimum maintenance, a material that can withstand hard installation conditions and minimum possible installation time, since this kind of lines usually requires a lot of work.

The other challenge was the installation of the water supply line. The conditions were also hard and they required a pipe in compliance with ASME standards.

Pexgol Solution

The Designer Engineer required China Harbour to install PE-x pipes for both lines.
Pexgol pipe systems was chosen due to its capabilities that allow the pipes to be drag on concrete, steel and all over the construction site making the installation efficient and fast. With other materials such as PE, tons of precautions to not damage should been necessary.
Pexgol pipes were also a great solution regarding possible water hammers caused by the hydrant trucks in case a fire develops, since the pipe can withstand them.

The pipes were connected with mechanical fittings, and they also didn’t required special treatment.
The installation with Pexgol pipes took x2.5 times less than any other material like PE. This pipes would have required special care to install the fittings, a much longer installation time and detailed supervision.
During the installation, local workers were trained on the field and complete the installation with great success.

Estudos de Caso Relacionados

Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015
Corrosion-resistant, lightweight piping for challenging mining environment.

Pexgol Enhances Lithium Brine Well Testing Manifolds

Gaana Servicios Mineros
Argentina

 | 

2024