Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Case Study Nº

88

Customer

AngloGold Ashanti
Brazil

|

2019

Working Conditions

Temperature: 30°C / 86°F | Pressure: 12 bar | Flow: 150 m³/h

Pexgol Pipes

Pexgol 225 mm (8”), Class 24

Application

Dewatering

Lenght

120 m / 393.70 ft

Categories

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

The Challenge

AngloGold had urgency in installing a new pumping line to remove effluents from the mine. Using traditional pipes could take up to two months to get the job done, considering all the preparation required to install such pipes. Furthermore, for AngloGold, using regular piping would mean putting its people in danger during the preparation to install the pipes and during installation itself.

Pexgol Solution

Using Pexgol allowed AngloGold to reduce the installation time by ten times, as a single continuous 120-meter-long pipe was used. Through an existing hole drilled on the mine the pipe was descended connecting its upper and lower parts. There was no need for people to be kept hanging at high heights to prepare any kind of structure to install the pipeline and no joints aside from the two extremes of the pipe were needed.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

It was an easy installation process, despite being the first time using Pexgol, and it was all done by AngloGold’s crew itself.
With a Volvo L90 loader and a JCB Loadall telescopic handler the crew completed the installation in 3 days

Related Case Studies

Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Installation of Pexgol Pipes for a Compress Air System.

Compressed Air System

Rav-Gon Printing House
Israel

 | 

2020
Transportation of River Water in Rough Terrain

Water Transport in Complex Terrain

Southern Copper Corporation
Peru

 | 

2019
Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015