Comparison of brine transport

Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

Case Study Nº

75

Customer

Albemarle Salar
Chile

|

2020

Working Conditions

Flow: 120 m3/h

Pexgol Pipes

Pexgol 200 mm (8”), class 10

Application

Brine transport

Lenght

112 m / 367.45 ft

Categories

Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

The Challenge

Albemarle salar decided to conduct a comparative test on their brine pipelines. The objective was to test the high resistance to scale formation that Pexgol pipes possess compared to conventional high-density polyethylene (HDPE) pipes.

Pexgol Solution

A Pexgol pipe was uncoiled by the main road from the salar to the parapet of 13D well, finally placing the pipe in the direction of 14D well to start the assembly according to its final disposition.

The flexibility of the Pexgol pipe allowed to fit easily into the layout, and its ability to be dragged greatly favored installation time.
Thanks to its high mechanical and impact resistance, Pexgol does not require the use of a special jacket.

For connection to the pump, a flanged coupling was used: clamp-type mechanical accessory with flange adjustment.

Pipe TypePexgol Cost vs OthersPexgol Total Investment Costs vs Others
Rubbed steel A53 Gr, B Sch. 201:1.41:2
Stainless steel 316L, Sch. 201:21:3
Titanium B862, Gr.2, 3 mm thk1:2.31:3.2
Polypropylene PP-H, SDR 171:3.81:4.2

 

Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
Sedimentation comparison: HDPE pipe after 30 days of use.
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
Sedimentation comparison: Pexgol pipe after 60 days of use.
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
After 30 days of operation, the HDPE pipe has incrustations with an approximate thickness of 50 mm.
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
Cleaning HDPE pipes presents a great physical wear and tear for operators, as they must hit hard to loosen the scale, which means more hours spent on maintenance.

Related Case Studies

Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019