Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

The Challenge

Commonly at Ashdod Sea Port (Israel) they require to transport all kinds of chemicals, acids and slurries to ship for export, from the port to the shipping boats.

In order to fulfill this procedure they installed cast steel pipes, which suffer from corrosion inside the pipe due to the chemicals after so many years carrying them. This steel pipes were very expensive to maintain, including frequent cleaning.

Pexgol Solution

An engineering firm specializing in the chemical industry, stated that Pexgol was the ideal solution for dealing with the challenges of the
line:

  • Pexgol’s proven ability to deal with acids.
  • Durability of the pipes.
  • The possibility of installing a 315 mm continuous pipe line without flanged connections in curved sections, saving the number of flanges and dramatically reducing weak points.

The Pexgol pipes were installed hanging with fixpoints on top of the current steel pipes, without damaging them. Omegas were installed as well (that couldn’t be done with PE pipes).
Took 10 days to install and operate the line, having the ships waiting in the water, the line started working immediately after completion.

Estudos de Caso Relacionados

Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022
Transport of Drinking Water in Harsh Terrain.

Potable Water Aqueduct

Acueducto y Alcantarillado de Bogotá
Colombia

 | 

2019