Skip to content

Navigating extreme conditions with Pexgol’s PE-X pipes

The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Estudo de Caso Nº

151

Cliente

Anglo American Perú
Peru

|

2023

Condições de Trabalho

Temperature: 15°-20°C (59° – 68°F) | Flow: 450 m^3/h | Pressure: 22 bar | Fluid components: Tailings with high percentage of solids 70%CW

Solução Pexgol

Pexgol 14″, SDR 11

Aplicação

Tailings transportation in copper mining

Comprimento

180 m / 590 ft

Categorias

Navigating extreme conditions with Pexgol’s PE-X pipes

The Challenge

In 2023, Anglo American Peru, a global mining leader, faced a significant challenge at its Quellaveco mine. The existing HDPE pipeline, designed for transporting copper tailings with high solids (70%CW) at a temperature of 15-20°C (59-68°F), a flow rate of 450 m³/hr, and a pressure of 22 bar, required an urgent upgrade. The pipeline needed to be rapidly installed on a steep slope with a 60-meter (197-foot) drop, to enhance the capacity of the concentrator plant and integrate cyclones into the system.

Pexgol Solution

The 14-inch PE-X pipes from Pexgol, with a total length of 180 meters in two segments of 90 meters each, were the chosen solution. Using Pexgol fittings like Electrofusion Couplers, Stub Ends, and Support Bridges, the installation was completed in approximately 7 days by a specialized team. The process involved a Pexgol vertical uncoiler and two cranes, ensuring a quick and efficient setup. The critical benefits of the Pexgol piping system, such as quick installation, high chemical and corrosion resistance, lightweight handling, and long lengths, were key to making it ideal for the project.

Estudos de Caso Relacionados

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019