Water transport in textile factory

Water Transport from a Borehole with Low Ph.

Estudo de Caso Nº

59

Cliente

CMT La Laguna
Mexico

|

2018

Condições de Trabalho

Pressure 4.5 bar, temperature at 40°C

Solução Pexgol

Pexgol 160 mm (6”), Class 15; Pexgol 225 mm (8”) Class 15

Aplicação

Water transport

Comprimento

2000 m

Categorias

Water Transport from a Borehole with Low Ph.

The Challenge

The company CMT La Laguna is a jeans textile factory (Levis brand), which due to its economic growth, saw the need to expand its factory, which led to an increase in processes and as a consequence greater water usage in the manufacturing process.

For the installation of the new pipe line to transport water, the line had to cross several sections of the factory. The client initially had thought to cross the factory from the inside, but this was complex due to the large amount of machinery already installed. It would also require a lot of labor for the assembly of the connections, due to the length of the line.

Pexgol Solution

CMT La Laguna decided to install Pexgol pipes. The pipes were offered in sections of 100, 150 and 200 meters, which greatly expedited the installation, since it required fewer connections. On the other hand, it allowed to save costs since the engineering team of Pexgol suggested the installation of the line on the roof, being able to save on supports and labor for the connections.

The client would not have been able to do this with other plastic pipes for example, since the metal sheets of the ceilings becomes very hot in summer (up to 60°C) and these would not resist.

At the factory, it was important that the pipeline look as neat as possible, and having many accessories exposed Pexgol made sure to provide a complete and visually adequate solution. Electrofusion fittings, “t” fittings and elbows were provided.

Thanks to Pexgol, the following savings were made:

  • The Pexgol installation team went to the field and trained the maintenance team of the factory, so that they can do the installation themselves without hiring a third party to do so.
  • Pexgol lent the welding tools so that the client did not have to invest in equipment.
  • Pexgol lent an uncoiling equipment to speed up the installation.

Estudos de Caso Relacionados

Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987
Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Gas Wells: Formation Water Treatment

Canacol
Colombia

 | 

2018