Skip to content

Water transport in textile factory

Water Transport from a Borehole with Low Ph.

Case Study Nº

59

Customer

CMT La Laguna
Mexico

|

2018

Working Conditions

Pressure 4.5 bar, temperature at 40°C

Pexgol Pipes

Pexgol 160 mm (6”), Class 15; Pexgol 225 mm (8”) Class 15

Application

Water transport

Lenght

2000 m

Categories

Water Transport from a Borehole with Low Ph.

The Challenge

The company CMT La Laguna is a jeans textile factory (Levis brand), which due to its economic growth, saw the need to expand its factory, which led to an increase in processes and as a consequence greater water usage in the manufacturing process.

For the installation of the new pipe line to transport water, the line had to cross several sections of the factory. The client initially had thought to cross the factory from the inside, but this was complex due to the large amount of machinery already installed. It would also require a lot of labor for the assembly of the connections, due to the length of the line.

Pexgol Solution

CMT La Laguna decided to install Pexgol pipes. The pipes were offered in sections of 100, 150 and 200 meters, which greatly expedited the installation, since it required fewer connections. On the other hand, it allowed to save costs since the engineering team of Pexgol suggested the installation of the line on the roof, being able to save on supports and labor for the connections.

The client would not have been able to do this with other plastic pipes for example, since the metal sheets of the ceilings becomes very hot in summer (up to 60°C) and these would not resist.

At the factory, it was important that the pipeline look as neat as possible, and having many accessories exposed Pexgol made sure to provide a complete and visually adequate solution. Electrofusion fittings, “t” fittings and elbows were provided.

Thanks to Pexgol, the following savings were made:

  • The Pexgol installation team went to the field and trained the maintenance team of the factory, so that they can do the installation themselves without hiring a third party to do so.
  • Pexgol lent the welding tools so that the client did not have to invest in equipment.
  • Pexgol lent an uncoiling equipment to speed up the installation.

Related Case Studies

Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

Comparison of brine transport

Albemarle Salar
Chile

 | 

2020
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014