Skip to content

Slurry Transportation

Replacement of HDPE Pipe for Pexgol

Estudo de Caso Nº

36

Cliente

Tizapa Mine
Mexico

|

2015

Condições de Trabalho

Pressure 100 Psi; Flow 225 mД/h; Specific Weight 1.2 t; Solids 20-30%.

Solução Pexgol

Pexgol 10” 250 mm, Class 15 (SDR 11).

Aplicação

Slurry transportation.

Comprimento

200 meters.

Categorias

Replacement of HDPE Pipe for Pexgol

The Challenge

Tizapa Mine formerly installed an HDPE line were they used to transport slurry. This pipe suffered several failures on the joints, so did the thermo-fusions and the stub-ends as well.

They determinate that the failures were caused by small water hammers on the line.

Pexgol Solution

Due to this special circumstances, Tizapa Mine decided to install Pexgol pipes for the following reasons:

  • Supplied in long lengths coils: Of 100 meters each, reducing possible failures in the joints.
  • It high resistance to water hammers.
  • Burst pressure: 3 times higher than nominal pressure.
  • Safe joints: They don’t deform neither detach caused by a pressure surge.
  • Quick installation: Coils were uncoiled in 1.5 work hours, without any complex equipment.

Estudos de Caso Relacionados

Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Installation of Pexgol Pipes in a Fish Processing Plant.

Fish Oil Transport at 36°C / 96.8°F

Guaymas Protein Company
Mexico

 | 

2018
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017