Skip to content

Backfill

Cement Slurry Injection to an Underground Mine

Estudo de Caso Nº

35

Cliente

Aguilar Mine
Argentina

|

2015

Condições de Trabalho

Fluids: Cement 450.2 g; Water 500 ml; Volume 670 cm.; Density 1.4 t/m. Pressure: Temporary pressures up to 33 k/cm2. Height difference: 300 meters.

Solução Pexgol

Pexgol 110 mm (4”) Class 24 (SDR 7.4).

Aplicação

Backfill

Comprimento

1,400 meters.

Categorias

Cement Slurry Injection To An Underground Mine

The Challenge

Due to this special circumstances, the client requested Pexgol pipes since they can be provided in 600 meters sections, they are flexible and highly resistant to abrasion and impacts.

The pipe sections were uncoiled hundreds of meters from the installation place, later they were descended with a hydraulic crane.

The end of the pipe was connected with a conical weight used as a guide to help it descend trough the robbins.

The ground was very harsh with sharp rocks, however the pipes were dragged, pulled and descended without problems.

The pipes were practically hanging from the surface of each level on the mine, supported by electro-fusion couplers. Despite the complicated conditions, the installation took only 60 net hours of work.

Pexgol Solution

Pexgol pipes were the optimal solution for this project, because it can be supplied in long lengths coils that makes the whole installation easier.

Pexgol is also known for its stress resistance, Pexgol’s crosslinking piping solution can withstand high amounts of axial and radial stresses, it only stretches up to 2% of its own length and it is capable to hold its own weight plus the water column.

Due to it great flexibility, the coil was uncoiled hundreds of meters away from the installation place, and it was dragged after to the right spot.

In order to descend the pipe through the open cast, it required only chains and a backhoe to hold it. Arcelor Mittal was very satisfied with the installation process, which was simple, and from their point of view, impossible to do it with other type of pipe.

Estudos de Caso Relacionados

Installation of Pexgol Pipes for a Compress Air System.

Compressed Air System

Rav-Gon Printing House
Israel

 | 

2020
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015
High Pressure potable water line

High Pressure Potable Water Line

Antofagasta Minerals, Pelambres Mine
Chile

 | 

2014