Well Drainage at Mining Dam

Installation of a Drainage System between a Well and a Mining Dam.

Case Study Nº

78

Customer

CODELCO – El Teniente Mine
Chile

|

2019

Working Conditions

Extreme temperatures -5° to 35°C / 25° to 95°F

Pexgol Pipes

Pexgol 250 mm (10”), class 15

Application

Dewatering

Lenght

1620 m / 5314 ft

Categories

Installation of a Drainage System between a Well and a Mining Dam.

The Challenge

The administration of the Carén reservoir, in the commune of Alhué (Chile), receives tailings from the El Teniente mine.

The western retaining wall of the reservoir needed to be widened by at least 30 meters. In order to do that a well had to be drained that was formed by leaks from the wall at its base. The extracted water had to be returned to the dam.
Also, the drainage work had to be done in just 20 days.

Pexgol Solution

The customer finally opted for Pexgol, despite the higher cost per meter, because the final cost of the installation, that only took one week, was widely offset against the installation of HDPE pipe that would have taken about a month and a half.

The advantage of Pexgol, in this solution, lies in the supply format in coils of long lengths, which made it possible to streamline its layout in the field, with no more than a dozen couplings, thus reducing assembly time.

In addition to the quick installation, technical assistance from the local team (Crosspipe Systems) was carried out with great agility and efficiency.
A total of 11 electrofusion fittings were installed.

Related Case Studies

Pexgol pipe was selected for the assembly of a muddy water transport line for a palm oil processing company.

Transport of Muddy Water for Palm Oil Extractor

Extractora Poligrow
Colombia

 | 

2022
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011
Installation of Pexgol Pipes in a Fish Processing Plant.

Fish Oil Transport at 36°C / 96.8°F

Guaymas Protein Company
Mexico

 | 

2018
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022