Water Transportation
Replacement of Carbon Steel Pipe for a Pexgol Pipe
Case Study Nº
42
Customer
Cargill
Mexico
|
2017
Working Conditions
Work done at -65 meters
Pexgol Pipes
Pexgol 100 mm (4″) SDR 11.
Application
Water transportation.
Lenght
50 meters.
Categories

The Challenge
In the plant “Purina” the water for production is taken from a well.
Originally they used carbon steel pipes to transport the water, which were useful only for a year, then they had to change the pipes since they suffered serious corrosion problems.
This phenomenon happened due to the high sodium content of the groundwater.
Pexgol Solution
The customer required a flexible pipe with a longer service life than carbon steel pipes to maintain a stable operation and minimize sudden stoppages for maintenance operations.
It was, therefore, decided to supply a pipe of 110 mm diameter in a single section which can withstand without any inconvenience the weight of the pump, the cables, the water column and the weight of the pipe.
Related Case Studies
Vertical Dewatering
Ferrexpo Poltava Mining
Ukraine
|
2019
Drainage System
BHP Pampa Norte – Cerro Colorado Mine
Chile
|
2020
Meltdown Water Transport
Codelco Andina, TADA 1-2 Project
Chile
|
2013
Drainage Lines in Underground Mine
Lundin Mining – Candelaria Norte Mine
Chile
|
2020