Skip to content

Water Transport with Low pH Level

Transport of acid water at high temperatures

Case Study Nº

2

Customer

Moa Nickel S.A. Sherritt
Cuba

|

2010

Working Conditions

Up to 65°C, 13 bars.

Pexgol Pipes

Pexgol 225 mm, Class 24 (SDR 7.3).

Application

Transportation of Acid Water.

Lenght

2500 m.

Categories

Level pH Low with Transport Water

The Challenge

Moa Nickel required to transport a big amount of overflow acid water from the sedimentation tanks to the slurry thickeners plant.

This overflow water substituted the reposition water that the slurry thickeners used.

The client debated regarding the use of a stainless steel pipe SS316L or thermoplastic flexible materials such as HDPE and polyethylene.

Pexgol Solution

At the end, Moa Nickel decided to use Pexgol pipes in long sections, instead of short ones of HDPE and polyethylene, as the best solution for the line, because this type of materials didn’t allow to work under the security standards in the allowable installation time.

The Pexgol pipe was installed in just 8 days with success. The fact that it didn’t require to create a sand bed and the high productivity for its installation in long sections, reduced to the half the installation time for this project. At the end, the client got 25% savings in comparison with the other possible materials.

Related Case Studies

Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019