Skip to content

Water Extraction from Wells

Water Extraction From Deep Wells (150 Meters)

Case Study Nº

27

Customer

Andacollo Mine
Chile

|

2015

Working Conditions

Extreme environmental temperatures (-5°C to 38°C).

Pexgol Pipes

Pexgol 110 mm, Class 24 (SDR 7.4).

Application

Water extraction.

Lenght

150 m.

Categories

Water Extraction From Deep Wells (150 Meters)

The Challenge

At Andacollo Mine, the process water was extracted from deep wells through a steel galvanized pipe. This pipes suffered repetitive failures on the joints and required a considerable long installation time. The client requested a pipe that could last longer, in order to minimize the stops at the plant for maintaining purposes.

Pexgol Solution

Golan provided 150 meters of Pexgol pipe 110 mm Class 24 (SDR 7.4) in one section. The pipe, once it was installed, managed to hold the weight of the pump, the cables and the water column, with no efforts.

For the pump maintenance, usually it requires to be extracted from the well. Thanks to Pexgol, Andacollo Mine managed to save time and money, due to the capacity to extract the pipe when is full of water, and there’s no need to do any drain.

Moreover, usually for a steel pipe it would have required more than 25 screwed joints, but with Pexgol it only took 2 (one to the pump and another one to the wellhead).

Related Case Studies

Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017