Water Extraction from Wells

Water Extraction From Deep Wells (150 Meters)

Case Study Nº

27

Customer

Andacollo Mine
Chile

|

2015

Working Conditions

Extreme environmental temperatures (-5°C to 38°C).

Pexgol Pipes

Pexgol 110 mm, Class 24 (SDR 7.4).

Application

Water extraction.

Lenght

150 m.

Categories

Water Extraction From Deep Wells (150 Meters)

The Challenge

At Andacollo Mine, the process water was extracted from deep wells through a steel galvanized pipe. This pipes suffered repetitive failures on the joints and required a considerable long installation time. The client requested a pipe that could last longer, in order to minimize the stops at the plant for maintaining purposes.

Pexgol Solution

Golan provided 150 meters of Pexgol pipe 110 mm Class 24 (SDR 7.4) in one section. The pipe, once it was installed, managed to hold the weight of the pump, the cables and the water column, with no efforts.

For the pump maintenance, usually it requires to be extracted from the well. Thanks to Pexgol, Andacollo Mine managed to save time and money, due to the capacity to extract the pipe when is full of water, and there’s no need to do any drain.

Moreover, usually for a steel pipe it would have required more than 25 screwed joints, but with Pexgol it only took 2 (one to the pump and another one to the wellhead).

Related Case Studies

Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018