1995

Working Conditions

Phosphoric acid up to 85%. The maximum working condition is 6 bar and 80°C.

Pexgol Pipes

Pexgol ½” (16 mm) up to 14” (355 mm).

Application

Phosphoric acid.

Lenght

1000 meters.

Categories

Transportation of Phosphoric acid in a potassium nitrate plant

The Challenge

Corrosion in the pipes and leakages in the connections. Frequent replacement needed. Fiberglas and Rubber lined steel pipes are hard to maintain.

Pipe materials tried prior to Pexgol:

  • Rubber lined steel pipes in short sections
  • Fiberglass pipes

Pexgol Solution

Haifa Chemicals use Pexgol (PEX) pipes very successfully, since 1995 in all their process.

Diametr of ½” (16 mm) up to 14” (355 mm)

Pexgol pipes are used in the Phosphoric acid plant, in the potassium nitrate plant and in the waste treatment plant. Pexgol pipes work with Phosphoric acid up to 85%, The maximum working condition is 6 bar and 80 degrees Celsius.

The Economic

The original mean time between failures (MTBF) was short due to frequent leakages. Changing to Pexgol eliminated faileures completely.

No maintenance required.

Related Case Studies

Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014