Transportation of Ore Slurry

Replacing steel pipes suffering from sediment formation

Case Study Nº

10

Customer

RUSAL, aluminum factory
Russia

|

2012

Working Conditions

Specific gravity was 1.510-1.550 kg/l, pressure 2 Bar (maximum 3-4 Bar), temperature of 99°C. Chemical composition: Na2O, AI2O3, F32O3, SiO2, CaO. Flow rate: 180M3/H.

Pexgol Pipes

160 mm class 15 (SDR 11).

Application

Industrial.

Lenght

15 meters with flared ends

Categories

Transportation of Ore Slurry

The Challenge

The main challenges were corrosion and scaling formation on the inner surface of existing steel pipes, causing a decrease of inner diameter of the pipes and consequent decrease of their throughput ability.

Pexgol Solution

Replacement of the existing 159 mm steel pipe with a 160 mm class 15 (SDR 11) Pexgol pipe.

The test line consists of three parts: One section is a white G-Pex pipe manufactured in Moscow, approximately 12 m long. Two more sections are 0.5 m long, each of black Pexgol pipe with flared ends, manufactured in Golan Plastic Products, Israel. These sections were connected by Plasson’s

Electro-fusion Pex-2-Pex couplers. During the entire operation the pipe was under continuous vibration because of a grinder operation.

The pipe was installed by the field team of Polimerteplo Group Llc accompanied by the field installation engineer of Gloan Plastic Products Ltd.

Related Case Studies

Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categories:

Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012