Skip to content

Transportation of Ore Slurry

Replacing steel pipes suffering from sediment formation

Case Study Nº

10

Customer

RUSAL, aluminum factory
Russia

|

2012

Working Conditions

Specific gravity was 1.510-1.550 kg/l, pressure 2 Bar (maximum 3-4 Bar), temperature of 99°C. Chemical composition: Na2O, AI2O3, F32O3, SiO2, CaO. Flow rate: 180M3/H.

Pexgol Pipes

160 mm class 15 (SDR 11).

Application

Industrial.

Lenght

15 meters with flared ends

Categories

Transportation of Ore Slurry

The Challenge

The main challenges were corrosion and scaling formation on the inner surface of existing steel pipes, causing a decrease of inner diameter of the pipes and consequent decrease of their throughput ability.

Pexgol Solution

Replacement of the existing 159 mm steel pipe with a 160 mm class 15 (SDR 11) Pexgol pipe.

The test line consists of three parts: One section is a white G-Pex pipe manufactured in Moscow, approximately 12 m long. Two more sections are 0.5 m long, each of black Pexgol pipe with flared ends, manufactured in Golan Plastic Products, Israel. These sections were connected by Plasson’s

Electro-fusion Pex-2-Pex couplers. During the entire operation the pipe was under continuous vibration because of a grinder operation.

The pipe was installed by the field team of Polimerteplo Group Llc accompanied by the field installation engineer of Gloan Plastic Products Ltd.

Related Case Studies

Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Transport of Drinking Water in Harsh Terrain.

Potable Water Aqueduct

Acueducto y Alcantarillado de Bogotá
Colombia

 | 

2019
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020