Transport of Compressed Air for Underground Mine

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Case Study Nº

101

Customer

HMC Gold
Chile

|

2021

Working Conditions

Pressure: 16 bar

Pexgol Pipes

Pexgol 160 mm (6”) Class 19

Application

Compressed air transport

Lenght

283 m / 928 ft

Categories

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

The Challenge

HMC Gold, in its Tambo de Oro mining unit, required to install a line of compressed air from the surface to the interior of the mine, through a chimney of approximately 2.5 meters, made with a raise boring drilling equipment.

Pexgol Solution

Having seen Pexgol’s experience at the Meridian mining company, where compressed air was also transported, HMC Gold decided to install a 283 meter Pexgol 160 mm, class 19 pipe.

Using Pexgol pipe allowed to eliminate the compressed air equipment inside the mine and to enable a main equipment on the surface. The system was enabled in less than 48 hours. They needed a pipe that resists a vertical 220 meters of chimney. Pexgol made work easier thanks to its long length, mechanical resistance to dragging and its good creep behavior.

For the installation, the pipe was de-coiled on the surface, then the sagging was started with the help of a weight at the tip and an upper containment with a support equipment. A concrete support was made at the top and connected to the compressor equipment via a 995 style stub end and flange coupling. A 995 style coupling to another line was installed at the bottom.

Related Case Studies

Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010
An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Water Supply & Fire Extinguisher Line

Cheddi Jagan International Airport
Guyana

 | 

2018