Skip to content

Transport of Compressed Air for Underground Mine

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Case Study Nº

101

Customer

HMC Gold
Chile

|

2021

Working Conditions

Pressure: 16 bar

Pexgol Pipes

Pexgol 160 mm (6”) Class 19

Application

Compressed air transport

Lenght

283 m / 928 ft

Categories

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

The Challenge

HMC Gold, in its Tambo de Oro mining unit, required to install a line of compressed air from the surface to the interior of the mine, through a chimney of approximately 2.5 meters, made with a raise boring drilling equipment.

Pexgol Solution

Having seen Pexgol’s experience at the Meridian mining company, where compressed air was also transported, HMC Gold decided to install a 283 meter Pexgol 160 mm, class 19 pipe.

Using Pexgol pipe allowed to eliminate the compressed air equipment inside the mine and to enable a main equipment on the surface. The system was enabled in less than 48 hours. They needed a pipe that resists a vertical 220 meters of chimney. Pexgol made work easier thanks to its long length, mechanical resistance to dragging and its good creep behavior.

For the installation, the pipe was de-coiled on the surface, then the sagging was started with the help of a weight at the tip and an upper containment with a support equipment. A concrete support was made at the top and connected to the compressor equipment via a 995 style stub end and flange coupling. A 995 style coupling to another line was installed at the bottom.

Related Case Studies

Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020