Skip to content

Slurry Transportation

Replacement of HDPE Pipe for Pexgol

Case Study Nº

36

Customer

Tizapa Mine
Mexico

|

2015

Working Conditions

Pressure 100 Psi; Flow 225 mД/h; Specific Weight 1.2 t; Solids 20-30%.

Pexgol Pipes

Pexgol 10” 250 mm, Class 15 (SDR 11).

Application

Slurry transportation.

Lenght

200 meters.

Categories

Replacement of HDPE Pipe for Pexgol

The Challenge

Tizapa Mine formerly installed an HDPE line were they used to transport slurry. This pipe suffered several failures on the joints, so did the thermo-fusions and the stub-ends as well.

They determinate that the failures were caused by small water hammers on the line.

Pexgol Solution

Due to this special circumstances, Tizapa Mine decided to install Pexgol pipes for the following reasons:

  • Supplied in long lengths coils: Of 100 meters each, reducing possible failures in the joints.
  • It high resistance to water hammers.
  • Burst pressure: 3 times higher than nominal pressure.
  • Safe joints: They don’t deform neither detach caused by a pressure surge.
  • Quick installation: Coils were uncoiled in 1.5 work hours, without any complex equipment.

Related Case Studies

Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020