Pumping Mining Effluents

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Case Study Nº

88

Customer

AngloGold Ashanti
Brazil

|

2019

Working Conditions

Temperature: 30°C / 86°F | Pressure: 12 bar | Flow: 150 m³/h

Pexgol Pipes

Pexgol 225 mm (8”), Class 24

Application

Dewatering

Lenght

120 m / 393.70 ft

Categories

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

The Challenge

AngloGold had urgency in installing a new pumping line to remove effluents from the mine. Using traditional pipes could take up to two months to get the job done, considering all the preparation required to install such pipes. Furthermore, for AngloGold, using regular piping would mean putting its people in danger during the preparation to install the pipes and during installation itself.

Pexgol Solution

Using Pexgol allowed AngloGold to reduce the installation time by ten times, as a single continuous 120-meter-long pipe was used. Through an existing hole drilled on the mine the pipe was descended connecting its upper and lower parts. There was no need for people to be kept hanging at high heights to prepare any kind of structure to install the pipeline and no joints aside from the two extremes of the pipe were needed.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

It was an easy installation process, despite being the first time using Pexgol, and it was all done by AngloGold’s crew itself.
With a Volvo L90 loader and a JCB Loadall telescopic handler the crew completed the installation in 3 days

Related Case Studies

Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019