Open Cast Mine Dewatering

Transportation of water with solids from an open cast mine

Case Study Nº

25

Customer

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2013

Working Conditions

Extreme environmental temperatures (-25°C to 40°C).

Pexgol Pipes

Pexgol 225 mm, Class 24 (SDR 7.4).

Application

Mine dewatering.

Lenght

4000 m.

Categories

Transportation of water with solids from an open cast mine

The Challenge

Collahuasi Mine required to transport water from the cast mine. Due to the harsh environmental conditions of the field, the engineering team decided to make a change on the type of material they have been using historically.

Pexgol Solution

A 4,000 meter Pexgol pipe was installed from the bottom of the cast mine to the load area. It required a Pexgol pipe 225 mm Class 24, in long sections of 320 meters that enabled an easy installation.

The Pexgol pipe was design to resist the working life cycle of the dewatering system, without suffering any damages on the pipe itself, the operations or the employees working on it.

Collahuasi Mine has become one of the Golan’s key clients regarding the use of dewatering lines among Chile’s mines. The pipe installed has been in use since 2013 with no failures.

Related Case Studies

Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022