Skip to content

Natural Gas Transportation with Pexgol

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Case Study Nº

110

Customer

YPF
Argentina

|

2022

Working Conditions

Fluid: Condensate natural gas | Temperature: 35°C / 95°F | Minimum Pressure: negative (vacuum) | Maximum Pressure: 2 kg/cm2 | Flow: 40.000 standard m3/d

Pexgol Pipes

Pexgol 160 mm (6”) , class 10

Application

Natural gas transportation

Lenght

600 m / 1968 ft

Categories

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

The Challenge

YPF is an Argentine energy company dedicated to the exploration, exploitation, distillation, distribution and production of electricity, gas, oil and other products related to the industry.

In its Vacas Muertas oil field, province of Mendoza (Argentina), the company had to replace 600 meters of carbon steel pipe, located between the crude oil treatment plant (PTC) and the gas compression plant. Over time, the section had reduced its internal diameter at different points of the trace, due to encrustations caused by corrosion and deposits resulting from humid gas condensation. This reduced the gas flow, and there was a risk of reaching a total obstruction of the flow.

As it is a continuous process, which does not allow accumulation of gas, it was necessary to carry out the work as quickly as possible with the shortest time of interruption of the flow to the gas plant.

Pexgol Solution

It was decided to install Pexgol pipes, which allow a quick installation and with the minimum amount of resources. This way, the corrosion process will be avoided, as well as the accumulation of scale due to the low absolute roughness of the internal walls of Pexgol pipes, allowing a continuous flow without obstructions over time.

The installation was completed with 3 coil of Pexgol 160 mm Class 10 pipe, the joints were made with electrofusion couplings, and the steel transitions with Pexgol flaring (stub-ends).

The installation was carried out in two working days, aerially on existing trestles, and with a minimum interruption of the process. The resources used were minimal: 3 operators with an uncoiler, a hydrocrane and a backhoe. The replacement with carbon steel would have taken a month with the company’s operational resources, and with a total cost 6 times higher than that required for the materials and installation with Pexgol pipes.

Related Case Studies

Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Transport of Formation Water with Hydrocarbons.

Formation Water Transport

ROCH
Argentina

 | 

2015
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019