Skip to content

Meltdown Water Transport

Pipe installation on a mountain

Case Study Nº

16

Customer

Codelco Andina, TADA 1-2 Project
Chile

|

2013

Working Conditions

Complex & harsh ground, 300 m altitude.

Pexgol Pipes

Pexgol 315 mm, Class 15 (SDR 11).

Application

Water transportation.

Lenght

3,300 m.

Categories

Pipe installation on a mountain

The Challenge

Codelco needed to transport meltdown water downhill at Andes Mountain range.

The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.

Pexgol Solution

Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.

The installation was simplified by the use of Pexgol long sections.

The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.

The installation was done in perfect timing with an optimal performance.

Related Case Studies

Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Grey Water Transportation

Recovered Water Transportation

Coeur Mexicana S.A. de C.V. Palmarejo
Mexico

 | 

2017