Skip to content

Industrial Waste Water to MBR Treatment Facility

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Case Study Nº

103

Customer

Chip Manufacturer
Israel

|

2021

Working Conditions

Design temperature: 50ºC | Pressure: 4 bar

Pexgol Pipes

Pexgol 400 mm (16”), class 10

Application

Industrial treated water transportation

Lenght

1000 m / 3281 ft

Categories

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to replace an 10” HDPE line that transported industrial waste water to an MBR treatment facility.

Pexgol Solution

Having seen Pexgol’s experience in other projects in Israel and around the world, the client decided to install a 1000 meter Pexgol 400 mm, class 10 pipe.

The client was able to install the entire system in only 20 days since the pipes were supplied in sections of up to 57 m. Furthermore, Pexgol pipes do not require expansion loops since the pipe is able to withstand contractions and elongations without deformation.

Using Pexgol pipes allowed a faster installation time, helping reduce the total cost of the project.
It minimized potential failure points. Also reducing the cost of connections along the line.

The installation was done on pipe-racks of 8.5 meter above ground. The connections were made using electrofusion welding and flanges. Additional fittings such as PE-X elbows and others were used.

Related Case Studies

Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

Free Chlorine Potable Water Supply

Rabin Medical Center
Israel

 | 

2020
Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categories:

Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021