Skip to content

High Pressure Potable Water Line

High Pressure potable water line

Case Study Nº

17

Customer

Antofagasta Minerals, Pelambres Mine
Chile

|

2014

Working Conditions

Gravity flow on harsh ground at 3,400 m altitude. 300 meters elevation difference gravity flow.

Pexgol Pipes

Insulated Pexgol pipe 140 cl 50 (SDR 4.3) polyurethane insulation / Flexwell-Pex 140×32.5/233.

Application

Safe water transportation.

Lenght

300 m.

Categories

High Pressure potable water line

The Challenge

“Pelambres” Mine required to install a safe water line to their new truck garage. The ground were the pipe needed to be installed was very complex with steep slopes.

The mine considered installing carbon steel pipes, but under those complicate conditions, the last 300 meter section was a very severe problem for the installation crew. The original plan considered 60 days for the assembly of that section.

Pexgol Solution

A pre-isolated Pexgol pipe was installed (Flexwell-Pex 140×32.5//233), that substituted the last 300 meters section of the carbon steel pipe.

The Pexgol pipe was provided in three long sections and welded in the ground by the Golan team, who also instructed the mine workers and the contractor.

The three sections were de-coiled and were welded by electro-fusion.

In the joints the polyurethane was replaced and reinforced.

The original schedule plan estimated 60 days for the installation, but with Pexgol it took only 15 days instead, with an optimal use of resources.

Related Case Studies

Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019