Skip to content

Fire Network Supply

Installation of a Fire Supply Network in a Oil Treatment Plant.

Case Study Nº

98

Customer

YPF
Argentina

|

2021

Working Conditions

Flow rate: 1000 m3/h | Temperature: 20°C | Maximum pressure: 15 kg/cm2

Pexgol Pipes

Pexgol 225 mm (8”) Class 15

Application

Fire network

Lenght

190 m / 623 ft

Categories

Installation of a Fire Supply Network in a Oil Treatment Plant.

The Challenge

YPF, Argentina’s national hydrocarbon exploration and production company, at its Oil Treatment Plant in the Vizcacheras area in Mendoza province, required a quick solution for the supply of water for its fire protection network.

This type of plant can never operate without having its fire network operational, and on this occasion it was necessary to change the source of the supply as quickly as possible, while still providing water supply and in the event of any emergency event. It was necessary to bury the pipe, crossing the foundations of the perimeter fence of the plant. The pipeline had to cross two sectors where light vehicles circulate and eventually large and weighing vehicles.

Pexgol Solution

It was proposed to install a coil of almost 200 m / 623 ft of Pexgol pipe, 225 mm diameter class 15, with flanged connections in the transitions corresponding to the impulsion pump and the ring of the fire network.

The installation was carried out using the minimum resources: an uncoiler and a hydro-crane, through which the maneuvers were carried out for uncoiling, deployment and connecting with three operators.

The depth of burial did not exceed 60 cm, without the need to encase the Pexgol pipe at road crossings. The task required two days of work, including the filling of the trench and the hydraulic test.

The same installation, carried out with carbon pipe, would have required 20 days using a welding equipment, at a cost of 3 times the installed value of the Pexgol 225 class 15 pipe.

Related Case Studies

Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Navigating extreme conditions with Pexgol’s PE-X pipes

Anglo American Perú
Peru

 | 

2023
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020