Skip to content

Cold Water Distribution for External Cooler System

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Case Study Nº

115

Customer

Chip Manufacturer
Israel

|

2022

Working Conditions

Pressure: 6 bars | Temperature: 8°C / 46°F

Pexgol Pipes

Pexgol 355 (14″), 400 (16″) & 630 (24″) mm, Class 15

Application

External Chiller System

Lenght

160 m / 525 ft

Categories

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to increase the capacity of energy in the factory by adding an external chiller system and they needed to finish the installation and implementation as soon as possible.

Pexgol Solution

Due to a successful experience in the past, the company decided to use Pexgol pipes due to the fast installation time, helping to maintain their operation schedule and reduce the total cost of the project.

Related Case Studies

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Installation of 3000 Meters Of PE-X Pipe for an Underground Mine.

Drainage Lines in Underground Mine

Lundin Mining – Candelaria Norte Mine
Chile

 | 

2020
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023
Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987