Carriage of Chemicals at Sea Port

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Case Study Nº

50

Customer

Ashdod Sea Port
Israel

|

2016

Working Conditions

High pressure, abrasion, constant water hammers

Pexgol Pipes

Pexgol 315 mm 90 Class 12 SDR 16.3

Application

Chemicals Transportation

Lenght

1.3 km

Categories

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

The Challenge

Commonly at Ashdod Sea Port (Israel) they require to transport all kinds of chemicals, acids and slurries to ship for export, from the port to the shipping boats.

In order to fulfill this procedure they installed cast steel pipes, which suffer from corrosion inside the pipe due to the chemicals after so many years carrying them. This steel pipes were very expensive to maintain, including frequent cleaning.

Pexgol Solution

An engineering firm specializing in the chemical industry, stated that Pexgol was the ideal solution for dealing with the challenges of the
line:

  • Pexgol’s proven ability to deal with acids.
  • Durability of the pipes.
  • The possibility of installing a 315 mm continuous pipe line without flanged connections in curved sections, saving the number of flanges and dramatically reducing weak points.

The Pexgol pipes were installed hanging with fixpoints on top of the current steel pipes, without damaging them. Omegas were installed as well (that couldn’t be done with PE pipes).
Took 10 days to install and operate the line, having the ships waiting in the water, the line started working immediately after completion.

Related Case Studies

Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017