Skip to content

Alumina Plant: Ore Slurry Transportation

Transportation of Bauxite Ore Slurry at 95°C / 203°F

Case Study Nº

52

Customer

Urals Alumina Plant – Rusal
Russia

|

2013

Working Conditions

High temperature

Pexgol Pipes

Pexgol 160 mm Class 15

Application

Slurry Transportation

Lenght

20 m

Categories

Transportation of Bauxite Ore Slurry at 95°C / 203°F

The Challenge

At Urals Alumina Plant, they required to renovate their carbon steel pipes where they transport bauxite ore slurry at 95°C / 203°F. Every year these lines were suffering from sedimentation problems and it was necessary to clean them every three months, involving man power and high costs.

Pexgol Solution

The client decided to replace the carbon steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance, lowering also costs.

The Pexgol pipes have been checked annually and even after 4,5 years of exploitation, the pipes have shown positive results. They don’t have to clean the pipes any more.

Related Case Studies

Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015