Transport of Compressed Air for Underground Mine

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Case Study Nº

101

Customer

HMC Gold
Chile

|

2021

Working Conditions

Pressure: 16 bar

Pexgol Pipes

Pexgol 160 mm (6”) Class 19

Application

Compressed air transport

Lenght

283 m / 928 ft

Categories

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

The Challenge

HMC Gold, in its Tambo de Oro mining unit, required to install a line of compressed air from the surface to the interior of the mine, through a chimney of approximately 2.5 meters, made with a raise boring drilling equipment.

Pexgol Solution

Having seen Pexgol’s experience at the Meridian mining company, where compressed air was also transported, HMC Gold decided to install a 283 meter Pexgol 160 mm, class 19 pipe.

Using Pexgol pipe allowed to eliminate the compressed air equipment inside the mine and to enable a main equipment on the surface. The system was enabled in less than 48 hours. They needed a pipe that resists a vertical 220 meters of chimney. Pexgol made work easier thanks to its long length, mechanical resistance to dragging and its good creep behavior.

For the installation, the pipe was de-coiled on the surface, then the sagging was started with the help of a weight at the tip and an upper containment with a support equipment. A concrete support was made at the top and connected to the compressor equipment via a 995 style stub end and flange coupling. A 995 style coupling to another line was installed at the bottom.

Related Case Studies

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Installation of Pexgol Pipes for a Compress Air System.

Compressed Air System

Rav-Gon Printing House
Israel

 | 

2020
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992