Replacement of a Steel Spool with Pexgol

Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Case Study Nº

106

Customer

Enap Sipetrol
Ecuador

|

2021

Working Conditions

Pressure: 10 PSI | Temperature: 71°C / 160°F

Pexgol Pipes

6”x4” steel eccentric reducer coated in Pexgol

Application

Formation water pumping

Lenght

n/a

Categories

Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water

The Challenge

Enap Sipetrol Ecuador, is a branch of the Chilean state oil company Enap, is the operator and owner of 42% of Block 28 in the southeastern area of Ecuador.

In their process plant where it was necessary to transport formation water, they had a steel spool coated internally with epoxy paint and it corroded easily due to the aggressiveness of the fluid.

Pexgol Solution

The client decided to replace the steel spool with Pexgol. It was installed in October 2021 and inspected in March 2022 and no type of corrosion or adhesion of solids was observed.

Related Case Studies

Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
Water Transportation through Shafts

Open Cast Mine Dewatering

Agnico Eagle Pinos Altos Mine
Mexico

 | 

2017
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017