Industrial Waste Water to MBR Treatment Facility

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Case Study Nº

103

Customer

Chip Manufacturer
Israel

|

2021

Working Conditions

Design temperature: 50ºC | Pressure: 4 bar

Pexgol Pipes

Pexgol 400 mm (16”), class 10

Application

Industrial treated water transportation

Lenght

1000 m / 3281 ft

Categories

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to replace an 10” HDPE line that transported industrial waste water to an MBR treatment facility.

Pexgol Solution

Having seen Pexgol’s experience in other projects in Israel and around the world, the client decided to install a 1000 meter Pexgol 400 mm, class 10 pipe.

The client was able to install the entire system in only 20 days since the pipes were supplied in sections of up to 57 m. Furthermore, Pexgol pipes do not require expansion loops since the pipe is able to withstand contractions and elongations without deformation.

Using Pexgol pipes allowed a faster installation time, helping reduce the total cost of the project.
It minimized potential failure points. Also reducing the cost of connections along the line.

The installation was done on pipe-racks of 8.5 meter above ground. The connections were made using electrofusion welding and flanges. Additional fittings such as PE-X elbows and others were used.

Related Case Studies

Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Installation of Pexgol Pipes for a Compress Air System.

Compressed Air System

Rav-Gon Printing House
Israel

 | 

2020